2. Calendriers et ressources
Objectives
-
Understand how capacity (availability × efficiency) influences the actual duration of tasks
-
Know how to assign resources and teams to a task
-
Understand the logic of calendars (project, task, result) and their combination
-
Recalculate the planning to see the impact on the Critical Chain and the buffer
​
Key concepts
​
-
Task capacity = combination of the capabilities of the assigned resources/teams (and/or the task schedule)
-
Resulting calendar:
-
Several resources → we merge (union) their working ranges (capacity = min)
-
Several teams → we cross (intersection) their ranges (capacity = min)
-
Resources + teams → we cross the two results (resource union) ∩ (team intersection)
-
Effective duration ≠ nominal duration: it depends on the ranges worked and the capacity
-
%20-%202025-11-27%20at%2014_04_edited.jpg)
Tips
You can update the catalogs at any time; the task editor will reflect new items.
Start simple: a standard calendar ( Mon- Fri, 9 a.m. to 6 p.m.), 2-3 resources, 1 team.
01
Catalogs settings
Why
Your assignments (resources/teams) and calendars determine the capacity and working ranges of the tasks.
Steps
-
Open Catalog Setup (or Catalogs) from the workspace toolbar
-
Select your JSON files (or use the default values) to:
-
Calendars (shifts per day, capacity),
-
Resources (name, efficiency, availability, schedule),
-
Teams (members, availability),
-
PERT (optional, used in your duration/variability calculations)
Apply. The data becomes available in the task editor.
02
Assign Resources to a Task
Steps
-
Open a task (tap/click in the list).
-
In Calendar / Resources:
-
Choose a resource (Select Resource menu)
-
Repeat to add multiple resources if necessary
-
-
​Observe:
-
The capacity of the task is updated (sum of availabilities × efficiencies)
-
If resources have a calendar, a resulting calendar is calculated automatically
-
​Rules (simplified)
​
-
Several resources → the resulting calendar is the union of work ranges per day
-
Resulting capacity = min of the capacities of the combined calendars (conservative approach)
-
If you delete all resources, the task returns to no resulting calendar (you can then select a manual calendar).​
%20-%202025-11-28%20at%2011_13_edited.jpg)
Advice
Assign critical resources first; see the impact on the actual duration before refining.
Check that the availability and efficiency of the resources are realistic (catalogs).
%20-%202025-11-28%20at%2011_19_edited.jpg)
Why is it useful
Several teams involved → we are restricted to really compatible slots.
Several individual resources → we open more available slots.
03
Assign Teams and Combine Calendars
Steps
-
Open a task, then in Calendar / Resources, add a team
-
Add other teams if necessary
​
Logic of combination
​
-
Teams: the intersection of the beaches is calculated (the common slots where all the teams can work)
-
If you have resources + teams:
-
We first calculate the union of resources,
-
Then we intersect with the intersection of the teams
-
The final capacity remains cautious: min of the capacities.​
-
Tips
-
Too many teams can drastically reduce common slots → monitor the actual duration
-
Prefer truly independent teams for parallel work (otherwise, sequence)
04
Re-plan and measure the impact
Steps
-
Open the ResultGrid panel (dates, gauges)
-
Click Apply to recalculate:
-
Effective durations (according to capacity and schedules),
-
Critical Chain (CC),
-
Buffer (size, position, consumption).
​
On the Gantt view:
-
The failed bars,
-
CC tasks (in evidence),
-
Start, Deadline, Buffer markers.
​
What happens "under the hood"
​
-
The actual duration of a task takes into account the ranges worked and the capacity
-
Multiple resources = union of niches; several teams = intersection; mix = intersection of the two worlds
-
The CC is recalculated on the augmented graph (precedences + strings of resources)
%20-%202025-11-27%20at%2016_00_edited.png)
Advice
-
Measure the effect of task-by-task assignments: sometimes adding a resource does not shorten if its calendar does not cover useful slots
-
Monitor the balance of the parallel branches (lanes) to avoid a bottleneck
05
Troubleshooting & Good Practices
Good practices
-
Don't hide parallelizable work in subtasks if you have multiple lanes.
-
Adjust Team size (lanes) at the level of the AI assistant to better exploit parallelism.
-
Keep main tasks (deliverable) - no micro-gestures.
Common problems
-
“The duration did not decrease after adding a resource”:
-
Check efficiency/availability,
-
Check the resource calendar (non-roverling ranges),
-
Too many teams → too narrow intersection
-
​
-
“Greyed task calendar”:
-
Assignments are present → the resulting calendar is priority
-
Delete assignments to go back to manual
-
​
-
“Capacity = 0”:
-
Check that the sum (availability × efficiency) is 0,
-
Check that the calendar is not empty.
-